Grovers Mill Dam Rehab Begins

Date:

Share post:

Repairs at the Grovers Mill Dam, off of Clarksville Road near Cranbury Road in West Windsor, were expected to get underway early this month, weather permitting. The work will provide for:

Installation of concrete-filled bags at the downstream end of the spillway concrete apron; grouting beneath the concrete apron at this same location; and repairs to the concrete facing of the upstream spillway structure wall faces. The work will require the Township to maintain a lowered water level in the Grovers Mill Pond reservoir for the duration of the project, in accordance with the approved State Water Lowering Permit.

The construction is expected to last about 30 days. The majority of the work will be performed off road. However, as part of the staging of equipment and/or materials, traffic on Clarksville Road may incur minor delays or diversions daily, between the hours of 9 a.m. and 4 p.m. No road closures are required for this work.

Related articles

Special meeting called for final public discussion of the Lawrence Community Center

Lawrence Township officials hope to wrap up discussions on the future use of the Lawrence Community Center (LCC)...

Landmark Robbinsville Town Center building takes on new role as town hall

Robbinsville has moved into a new municipal building, marking the transformation of one of the most prominent structures...

Community turns out for Allentown Spring Stroll

Area visitors turned out in force to brave the cooler-than-usual weather on Sunday, April 26, 2026 to attend...