WW Projects Move Forward

Date:

Share post:

The sewer at Alexander and Wallace roads is due to be fixed between Monday, June 25, and Monday, July 9, according to West Windsor business administrator Christopher Marion. The township has awarded a $65,”933 contract to Roy Conover and Sons, a local company.##M:[more]##

The roads are expected to be closed intermittently while the work is completed. The project will include replacing one existing manhole and installing another manhole. The existing pipes will be re-lined.

The problem started when the area flooded during a rainstorm in March. As a result, the township awarded an emergency bid, and may be eligible to be reimbursed up to 75 percent of the cost by FEMA.

The township is conducting a traffic study of Canal Pointe Boulevard. The study will cost $75,”000 and will be completed before the end of the year.

According to township engineer James Parvesse, the study will determine the best way to make the roadway safer for drivers and for pedestrians. The township has budgeted 1.2 million for improvements over the next four years.

Related articles

Bonne Giglio wins Democratic Party nomination for Lawrence Council and faces independent challenger

Incumbent Township Councilwoman Bonne Giglio earned the Democratic Party's nomination to run for a one-year unexpired term, but...

No surprise in Mercer County Democratic and Republican Party primary contests

There were no surprises, with the exception of the Mercer County Board of County Commissioners, in the results...

A fresh start for the Allentown Farmers Market

The Allentown Farmers Market is moving to High Street with new leadership and more room to grow. Katrina Carroll...

Foundation gives retired racehorses a future

A horse once headed for slaughter surged through traffic, scaffolding and parked cars on a Manhattan street, carrying...