Water Plant Back in Service

Date:

Share post:

In Plainsboro, the United Water Princeton Meadows wastewater facility has made progress towards regaining full capabilities after Hurricane Irene shut down its operations in late August. An announcement was made on Wednesday, January 4, signaling that things have returned to normal.

“The plant lost all power during the height of Hurricane Irene, and the facility sustained significant damage to its equipment due to the flooding, automatically halting all operations. We are very pleased to report that as of today necessary repairs have been finalized and damaged equipment has been repaired or replaced,” said Director of Operations Rick Pfleiderer.

Pfleiderer said massive equipment failures during Irene included the facility’s main transformer, emergency generators, transfer switches, and laboratory testing equipment, among other systems.

Twenty-four hours following Irene the plant was running again thanks to temporary equipment. But when the plant was unable to drain into Cranbury Brook as normal, United Water’s customers were prompted not to use any appliance that drains into the sewer system such as washing machines or dishwashers.

Related articles

Special meeting called for final public discussion of the Lawrence Community Center

Lawrence Township officials hope to wrap up discussions on the future use of the Lawrence Community Center (LCC)...

Landmark Robbinsville Town Center building takes on new role as town hall

Robbinsville has moved into a new municipal building, marking the transformation of one of the most prominent structures...

Community turns out for Allentown Spring Stroll

Area visitors turned out in force to brave the cooler-than-usual weather on Sunday, April 26, 2026 to attend...